100% Land Acquired For Mumbai-Ahmedabad Bullet Train; 341 Kms Pier Constructed! – Trak.in – Indian Business of Tech, Mobile & Startups

8

Significant advancements in the Mumbai-Ahmedabad bullet train project have been announced by the Ministry of Railways. As per the latest update shared by the ministry, there has been substantial progress in the key construction phases and the project is nearing completion.

Rail Ministry Announces Major Milestones in India’s First Bullet Train Project

In a recent tweet, the rail ministry said that the “Substantial strides towards accomplishing the Nation’s first #BulletTrain project, with key construction phases underway”.

There comprehensive progress report highlights several critical milestones achieved as of July 31, 2024 for the PM’s dream project:

  • Land Acquisition: The required land totalling 1,390 hectares has been 100% successfully acquired, which marks the completion of the most crucial step ensures that the construction can proceed without any further delays related to land disputes.
  • Pier Foundation: Laying the groundwork for the elevated track structure, the construction of the pier foundations has reached 341 kilometres.
  • Pier Construction: Out of the total required, 324 kilometers of piers have been completed, forming the base of the future bullet train track.
  • Girder Casting: The casting of girders, which are essential for supporting the railway tracks, has reached 231 kilometers.
  • Girder Launching: The installation of these girders has progressed to 200 kilometers, further solidifying the structural integrity of the route.
  • Rail Installation: As the project advances, the laying of the rail tracks is underway, with ongoing efforts to ensure timely completion.

India’s First Bullet Train Project: ₹1.08 Lakh Crore Investment for 508 km Corridor

The government is spending almost Rs 1.08 lakh crore on the project. Country’s 1st bullet train shall traverse the states of Gujarat, Maharashtra, and the Union Territory of Dadra and Nagar Haveli. 

The bullet train that shall run on the Mumbai-Ahmedabad bullet train corridor, shall stretch 508 kms and reach a speed of up to 320 km/h.

Highlighting the impressive strides made towards accomplishing the nation’s first bullet train project, this update by the Ministry of Railways’ tweet underscores the commitment to enhancing India’s rail infrastructure with state-of-the-art technology.